Aligning any rotating machinery, what are the pre-alignment checks to be done?
Before proceeding with pre-alignment, below checks need to be done. – First thing to check the machine is properly secured to foundation. – Check for any excessive run-out conditions i.e. Eccentric coupling bore, Bent Shaft etc. – Machine to base plate interface problems i.e. soft foot. – Ensure that no piping loads are coming on the machine, with proper stress analysis and to avoid nozzle loaRead More…